THE SCOPE:
Installation of Modules and all associated Mechanical works for the Sulphur Units 50 and 60. This includes all Material Handling, Preservation, Structural Steel Erection, Piping Tie in’s and Testing / Commissioning of the units. Associated works included Heavy Lift, Site Preparation, Scaffolding, Site Wide Services.

TYPE OF PROJECT:
Facility

MANAGEMENT OF SUB-CONTRACTORS:
Phoenix Industrial is Managing Several Sub Trades Including, Electrical, Instrumentation,  Scaffolding, Insulation and Cladding, and Non Destructive Testing, Civil, Surveying, Heavy Lift, and Site Wide Services.

MANPOWER REQUIRED:
More than 422,000 Man Hours

SAFETY RECORD:
Zero Lost Time Incidents to date