THE SCOPE:
General contractor and construction management of the central processing facility. This included all mechanical, piping, structural, glycol tracing, and grout work for the pumps and vessels.
TYPE OF PROJECT:
Central Processing Facility
MANAGEMENT OF SUB-CONTRACTORS:
There was a long list of subcontractors managed on this project. The disciplines varied from: offsite fabrication, logistics and trucking, third party safety and screening, surveying, engineering, mechanical, rigging, concrete, earthwork, pressure testing, and NDE/NDT.
MANPOWER REQUIRED:
Over 500 employees on site over a 12 month period.
SAFETY RECORD:
Completed with 0 lost time incidents.